houserepairgude
Home News Contakt Info-Order Site Map

You are in: Building the House

You Have Accomplished - Part 1

Look at how even you annex accomplished. You annex your building abundance, you’ve arranged your

loan, and you annex a box course you can indispensable with and are able to finance.

You’ve completed the broad bigness of paperwork that includes any leading permits and insurance policies.

You annex located most of your subs and annex contracts with them.

You’ve visited indefinite assistance houses and worked out your accounts for bricks, concrete, and lumber.

Congratulations.

You’ve reached the age you cue might never come.

You’re ready to day one building.

What is the proper sequence of steps in building the box, and how extensive will each accept? Let’s assemble a document of them.

1. Staking the abundance and box: 1–3 hours

2. Clearing and excavation: 1–3 days

3. Ordering utilities, transitority electric function, and a portable toilet: 1 hour

4. Footings (steps 3 and 4 can be reversed). First inspection must be fictional before pouring: 1 day

5. Foundation and earth treatment, then foundation survey: 1 week

6. Rough-ins for plumbing, provided on a slab, and inspection: 2–4 days

7. Slabs, basement, and garage: 1–2 days

8. Framing and drying-in: 1–3 weeks

9. Exterior siding, trim, veneers: 1–3 weeks

10. Chimneys and roofing: 2 days–1 week

11. Rough-ins can be done while steps 9 and 10 are in progress: 1–2 weeks

12. Insulation: 3 days

13. Hardwood flooring and underlayment: 3 days–1 week

14. Drywall: 2 weeks

15. Priming walls and “pointing up”: 2 days

16. Interior trim and cabinets: 1–2 weeks

17. Painting: 2–3 weeks

18. Other trims, such as Formica, ceramic tile, vinyl floors: 1 day–1 week

19. Trimming out and finishing plumbing, mechanical, and electrical and hooking up utilities: 1–2 weeks

20. Cleanup: 2–3 days

21. Floor-mat and/or hardwood floor finish: 3 days–1 week

22. Driveway (if concrete, can be poured anytime after course 14): 1–3 days

23. Landscaping: 1–3 days

24. Final inspections, surveys, and closing of construction loan and interim loan:

1–3 days

25. Enjoying your native: a lifetime

Print Version

Next Article




You Have Accomplished - Part 1
Staking the Lot and House (1–3 hours) - Part 1
Staking the Lot and House (1–3 hours) - Part 2
Staking the Lot and House (1–3 hours) - Part 3
Clearing and Excavation (1–3 days) - Part 1
Clearing and Excavation (1–3 days) - Part 2
Utilities Hookup (1 hour)
Footings (1 day) - Part 1
Footings (1 day) - Part 2
Foundations (1 week) - Part 1
Foundations (1 week) - Part 2
Rough-in plumbing (2–4 days)
Slabs — for Heated Areas (1–2 days)
Framing (1–3 weeks)
Exterior Siding, Trim, or Brick Veneer (1–3 weeks)
Chimneys and Roofing (2 days–1 week)
Rough-ins (1–2 weeks)
Insulation (3 days)
Hardwood Flooring and Underlayment(3 days–1 week)
Drywall (2 weeks)
Priming Walls and “Pointing Up” (2 days)
Interior Trim and Cabinets (1–2 weeks)
Painting (2–3 weeks)
Other Trims (1 day–1 week)
It’s time for the plumber to finish his work.
Cleanup (2–3 days)
Carpet (3 days–1 week)
Driveway (1–3 days)
Landscaping (1–3 days)
Final Inspections, Surveys, Loan Closings (1–3 days)
Be the General Contractor - Part 1
Be the General Contractor - Part 2
Be the General Contractor - Part 3
Find a Good Carpentry Crew
Time Involved
Work by Phone - Part 1
Work by Phone - Part 2
You Can Get a Loan
Be Persistent!
Alternatives to Being Your Own House Contractor
The Budget Comes First
Land Is the Second Step
Choosing the Right Land
Sloping Lots
Other Considerations
Let the Brokers Do the Work - Part 1
Let the Brokers Do the Work - Part 2
How Much Should You Spend on Land? - Part 1
How Much Should You Spend on Land? - Part 2
The House Plans - Part 1
Cutting Construction Costs
Make Changes Early - Part 1
Make Changes Early - Part 2
Parts of Plans - Part 1
Parts of Plans - Part 2
Cost, Appraisal, Decision!
Your Subcontractors and Professionals
Finding Your Subs - Part 1
Finding Your Subs - Part 2
Asking for Bids - Part 1
Scheduling Your Subs
Working with Subs
Paying Your Subs - Part 1
Paying Your Subs - Part 2
Additions, Renovations, and Extreme Makeovers to an Existing Home
Building an Addition
How to Estimate Costs
How to Finance an Addition
Remodeling: Renovation or Restoration - Part 1
Remodeling: Renovation or Restoration - Part 2
Tearing Down and Building Up
Plaster Removal.
Foundation, - Part 1
Foundation, - Part 2
Roofing.
Chimney. - Part 1
Drywall or Plaster.
Final Inspection and Loan Closing. When all is done, be sure your subs have
Starting from Scratch – the Extreme Makeover
Spreadsheets - Part 1
The Process of Estimating - Part 1
The Process of Estimating - Part 2
The Process of Estimating - Part 3
Balancing Costs
Cost Breakdowns - Part 1
Cost Breakdowns - Part 2
Cost Breakdowns - Part 3
Cost Breakdowns - Part 4
Cost Breakdowns - Part 5
Inspections Required
Final Details - Part 1
Doing Your Own Labor
The one-time close construction loan - Part 1
The one-time close construction loan - Part 2
How a Construction Loan Works - Part 1
How a Construction Loan Works - Part 2
Two Homes?
Cash Needed
Qualifying for a Loan
Different Products - Part 1
Different Products - Part 2
Delivery of Materials
Buying at Builders’ Cost
Paying Your Suppliers
Bookkeeping

Best Articles

Different Products - Part 1
The suppliers that you will be buying from are listed in this folio by the type of products they sell.

Staking the Lot and House (1–3 hours) - Part 2
It doesn’t contain to, exceptionally provided your at ease is on a doozer collection, unless the building code demands this.

Rough-in plumbing (2–4 days)
If you accept a basement with plumbing or provided you are building the building on a concrete slab
© 2008 Propan